White Cloud Dam Update
City of White Cloud Regular Meeting September 2, 2025. James Ensing delivered Wade Trim’s “Phase One Dam Presentation.” It included their $55,000 proposal that Council approved. Of that, $40,000 is to go toward an “Alternative Analysis” that includes a re-evaluation of the repair/replace and active/passive removal options covered in the Disposition Feasibility Study completed this spring by GEI Consultants.
Newly introduced were two alternatives presented as Dam Deregulation. The one shown here expands the width of the dam in what Wade Trim felt might not be governed by State dam regulations. The added earth, shown in yellow, covers Rotary Park. A second variation placed fill to the east (upstream) of the current dam. There was no information provided concerning fish passage for these alternatives.
If the City elects to keep S State Street (S Silver Drive) open, Wade Trim estimates a bridge will cost $2 Million.
As to timing, EGLE’s April 1st Order set November 3, 2025, for the City to finalize its plan for long-term remedial action (the work covered in Wade Trim’s proposal). In an earlier City Council meeting, EGLE’s representative indicated a reasonable extension would be considered. On September 2, 2025, Wade Trim’s representative told the Council the work outlined in its proposal might take until Spring 2026 to complete.
White Cloud Dam Phase 1 Scope & Fee slide presentation from September 2, 2025, given by Wade Trim during meeting of White Cloud City Council.