Two Step Strategy Emerging – July 21, 2026 Meeting of White Cloud City Council
The Special Meeting of the City of White Cloud, July 21, 2026, laid out the emerging strategy to remove the dam owned by the City. The storms in the first half of April this year apparently convinced an entourage of State and Federal officials of the urgency. It seems they have coalesced around a two-step approach. Step one, optimize safety. Step two, implement the most economical long-term solution.
Much like a detective novel, where all the plot elements make sense only after reading the final page, the key to making sense of this two-hour-long meeting was the mayor’s remarks in the final three minutes before adjournment. Back during the peak of the April flood, Mayor Brian Miller met for an hour with “Representatives from the State, as well as a representative from the federal government, representatives from EGLE as well.” “They looked at both dams pretty well, at that point in time.” The other dam was Hesperia.
“How do you take a one-hour meeting standing by the dam and present all that verbiage at a meeting like this.” Surely also on the mayor’s mind was how best to prepare for the City Council’s vote set for September 1. How to prepare the six council members, all of whom were present in the Newaygo County Council room, but also the community, about a hundred showing up for the fourth special dam meeting.
Step One, which James Ensing of Wade Trim titled Alternative No. 4 – Removal of Existing Gate Structure, would get rid of existing gates, stoplog structures, and all associated frameworks at both main and auxiliary spillways. This step increases the discharge, nearly eliminating the possibility of clogging of the bar grates with floating vegetation, while reducing the chance for accidental or malicious acts that would impound floodwaters behind the questionable dam.
Where to come up with the estimated $50,000 to $100,000, didn’t get answered.
Step Two, Alternative No. 3.1 Dam Removal with Passive Restoration, takes out the primary spillway and trims back the least possible amount of the current earthen embankment. Matching the river channel below the dam toe with the higher stretch about a mile upstream at the M-20 bridge is accomplished with a two-stage channel. Disposing excavated spoils onsite, not trucking them away, is the major cost reduction previously not considered. Estimated costs dropped to between $5.2M and $5.8M from the earlier $9.3M estimated in the White Cloud Dam Disposition Feasibility Study.
More daunting than environmental issues seem to be funding.

Thomas Horak, EGLE Dam Safety Unit (left) and James Ensing of Wade Trim
Thomas Horak’s comments demonstrated the State’s commitment to the two-step approach. He indicated EGLE would seriously consider permitting the intermediate Alternative 4 if Alternative 3.1 were in the works to follow. He then provided history of the three grant rounds where the State set up $45M for dam risk reduction. White Cloud and Hesperia both were recipients, but Horak said that money is used up. The proposed 2027 State budget doesn’t include any more. Still he remains “hopeful.”
City commissioner Anuci asked, if White Cloud were to approve the two-step strategy and then State funds were to become available later, would EGLE still consider a grant request from the City? “Absolutely,” was Horak’s response. He then offered, when they had that program funded, the largest grant was “four million and change” to help fund removal of another ‘High Hazard’ dam. He even speculated, if Lansing were to approve “a supplemental in the budget tomorrow,” EGLE should be able to make those funds available in 2027, and White Cloud would get the email.
During the Council members’ comments, Becker hoped funding could be found for a swimming hole. Shears, in preparation for her September 1st vote, had expected more details from Wade Trim. The council members who at prior special meetings had been advocates for keeping the dam and lake made no comment.
The mayor summed it up, “Council is going to have some interesting conversations about this because we do want to do what’s best for the community. And also we do have a budget. We have to figure how to come up with 4 million that…” He broke off mid-sentence, then continued, “You know, fund the rest of the dam, if that’s what we want to do, along with ongoing maintenance.”

Mayor Brian Miller (left) with City Manager April Storms

Additional Resources
White Cloud Dam Disposition Feasibility Study
White Cloud Dam Impoundment page. Includes timeline and links to all publicly available information concerning the dam, going back to the Trout Unlimited suit in 1989.
White River Watershed Impoundment page. Includes details on all recorded impoundment within the watershed plus useful background information.
WRWP Research, Reports, and Records page. Included on this page is access to the graduate level thesis on the impact of climate change on the White River watershed fishery.
Wade Trim Phase 1 Scope and Fee proposal. September 2, 2025. 7 page pdf with 13 slides, including a project schedule and the fees for the work leading to the presentation on July 21, 2026.
Step One. Alternative No. 4 – Removal of Existing Gate Structure
Step One of the Two Step Strategy had not been previously proposed, either by Wade Trim at earlier presentations to White Cloud or in the White Cloud Dam Disposition Feasibility Study. In Wade Trim’s Summary Table it shows that this interim step “Buys Time.” One commissioner asked why not go straight to Alternative No. 3.1. Someone replied, “It gets EGLE off your back.”
One consideration included in the White Cloud Dam Disposition Feasibility Study not mentioned in Wade Trim’s presentation is use of the gates to hold back the river as the spillways downstream are removed.
Step Two. Alternative No. 3.1 – Dam Removal with Passive Restoration
Step Two would restore the river from the toe of the dam to the M-20 Bridge east of White Cloud. Slide 18 is the modified profile of the floodplain shown in the White Cloud Dam Disposition Feasibility Study, but with a portion used for “spoils” (excavated soil). That cost saving, when combined with greater funding potential from fish passage, may makes this alternative the most probable final resolution to accomplish.
Summary of Alternatives
- Alternative No. 1 – Repair Existing Dam
- Alternative No. 2 – Modify Existing Structure to Deregulate Dam
- Alternative No. 3 – Dam Removal with Active River Restoration
- Alternative No. 3.1 – Dam Removal with Passive Restoration (modified for July 21, 2026 presentation)
- Alternative No. 4 – Removal of Existing Gate Structures (added for July 21, 2026 presentation)
- Alternative No. 5 – Enlarge Primary Opening to Deregulate Dam (not covered during July 21, 2026 presentation)
Bridge Options
Alternative No. 3.1 would allow for a bridge if the funding becomes available.

Swimming Pond Option
Commissioner Becker made a passionate appeal to keep some form of swimming hole. Below is a concept drawing from the presentation showing one adjacent to Charles S. Smith Park. James Ensign of Wade Trim indicated it would be possible, but that no estimate had been made of the costs. To get water to the pond and keep it circulating, either a channel or piping would need to be run from a higher elevation up stream.

Deregulated
In the presentation on July 21, 2026, Wade Trim indicated that several of the Alternatives, once completed, should be considered deregulated.
What does this mean? It’s not a dam. More specifically, the replacement for the current dam should no longer be considered a dam subject to the Michigan Natural Resources and Environmental Protection Act (MNREPA). Once the project is complete – construction done and everything signed off – White Cloud would have no more dam inspections, no more dam licensing renewals, nor other requirements under the dam section of MNREPA. However, there may still be other sections of MNREPA that apply.
Pending Changes to the law
As of the July 21, 2026, White Cloud meeting, the Michigan House of Representatives had passed House Bill No. 5485, on a vote of 100 to 8 (a substantial bipartisan margin). The proposed revisions to the dam section of MNREPA incorporate many of the recommendations made by the Governor’s Dam Safety Task Force. The Task Force was formed following the double failure of Edenville and Sanford Dams in 2020. The Michigan Senate has yet to vote and the Governor is yet to sign.
It should be noted that if the House version is enacted, there will be more ongoing dam inspections, and most probably a greater discharge rate requirement. A greater discharge rate would mean a larger spillway and most surely a greater cost to build. Postponing the decision to become “deregulated” might make existing dams subject to more stringent criteria when their license comes up for renewal. Kicking the can down the river could cost more.
Wetlands

Wetlands post drawdown of Lake White Cloud.
As a permit requirement for the ordered drawdown of Lake White Cloud in the summer of 2025, the City hired Streamside Eco to conduct a wetlands survey. As shown in their aerial plan, 52 acres had become wetlands. The upstream limit is approximately 1100 feet north of M-20.
The consultant pointed out that “Permits would be required from the EGLE prior to conducting any regulated activities within the wetland. Regulated activities include, but are not necessarily limited to, excavating, filling, grading (essentially movement of soils), construction, altering hydrology (draining), and use (e.g. directing and storing water).”
Alternative No 3.1, Step Two of the strategy, calls for on-site placement of spoils that are now designated wetlands. To obtain the permits to fill over the wetlands, the law permits mitigations. Even with the cost of mitigations, Wade Trim anticipate a major savings over trucking the material off site.
The engineer from EGLE’s Dam Safety Unit was reluctant to speak for those in that Wetlands portion of EGLE, but indicated they have already been made aware of the situation.
When Michigan implemented wetland protection regulations in the late 1970s, it became one of only three states allowed under the federal Clean Water Act to have regulatory oversight within its borders. In 2023 the US Supreme Court decided Sackett v. EPA. It ruled federal law only applies to “bodies of water that maintain a continuous surface connection to traditional, navigable waters.” To scale back Michigan’s EGLE regulatory authority to this revised federal criteria, Michigan House representatives introduced House Bill 5536. It passed the House June 4, 2026, the vote was 57 Yeas, 51 Nays. To become law, it must also pass the Michigan Senate and get the Governor’s signature.
If and how this legislation might affect the implementation of Alternative No. 3.1 is uncertain at this point.
Thermal Pollution
Water temperature determines which fish species can survive in a river. Any impoundment exposed to the sun absorbs heat. The larger the pond’s surface area and the slower the water moves through it, the greater the warming.
The White River is Michigan’s southernmost cold-water fishery. In some stretches of the White, Salmon and trout are already near the limit of their temperature tolerance, making them especially vulnerable to climate change and land-use changes. Many agricultural tributaries in the southern watershed are already too warm to qualify as cold-water streams.
Groundwater supplies most of the White River’s base flow and keeps the river cool. As groundwater is depleted faster than it is recharged, less cold water enters the river, stream temperatures rise, and suitable habitat for salmon and trout declines.
The White River watershed contains 15 registered impoundments. The former pond above White Cloud Dam was the largest, covering 133 acres. After Lake White Cloud was drawn down, the two EnviroDIY monitoring stations, one above and one below, detected a measurable reduction in downstream day-time summer water temperatures. Step Two, Alternative No. 3.1, would make that improvement permanent.
Since White Cloud acquired the dam from Consumers Power in 1950, the Michigan Department of Natural Resources has documented its thermal impacts in successive Status of the Fishery Resource Reports. Even releasing water from the bottom of the impoundment failed to reduce downstream temperatures after sediment accumulated near the pond’s surface.
A recent graduate-level study of the White River evaluated how climate change could affect fish habitat through the end of the 21st century. Under the worst-case scenario, much of the watershed could lose its cold-water fishery status.
Farther downstream, the Hesperia Dam creates a similar thermal problem. Its 8-foot head forms a 50-acre impoundment that warms the river. Because sea lamprey control—a primary purpose of the proposed replacement project—may be achieved with a barrier only 2 to 4 feet high, as reported by the Great Lakes Fishery Commission, a substantially smaller impoundment could reduce thermal impacts while still meeting management objectives. Great Lakes Fishery Commission – Barriers
How big was the April 2026 flood?
Estimates of the April flood ranged from a 40-year event to more than 200 years, with some even suggesting a 500-year flood. Yet neither the EGLE engineer nor Wade Trim could provide an official estimate based on state or federal data.
The White Cloud Dam Disposition Study examined the hydrology of the 81-square-mile watershed above the dam using rainfall records from the Newaygo County Road Commission weather station on M-20 west of M-37. That data could—and should—be used to model the April storm. If it exceeded the 200-year event, it would become the new flood of record and could change the design discharge for a replacement structure. Even if it falls short of that threshold, the storm’s magnitude could still affect design decisions, including the amount of the earthen embankment removed under Alternative 3.1.
Further hydrologic study is also needed to better understand the relationship between the White Cloud and Hesperia dams. The mayor noted that the drawdown area behind the White Cloud Dam filled during the flood without failing. Although the White Cloud DPW stopped recording water levels after the drawdown, photos taken on April 16 show water levels similar to those during the 2025 Russell Gilbert Memorial Kids Free Fishing event.
The temporary storage provided by the White Cloud impoundment may have reduced flooding at Hesperia Dam. Determining whether that occurred would be valuable before finalizing Hesperia’s design, particularly for managing construction risks.
Fish Passage
Alternate No. 3.1 would provide fish passage to not only Salmon and Trout, but also a host of native species such as Walleye, White Sucker, Creek Chubs that move upstream to spawn, then often run downstream during low water and winters. Fish passage is also being considered as part of the dam replacement project for Hesperia.
Access to spawning grounds used by lake run species (anadromous), i.e., Coho, Chinook and Steelhead, has been curtailed, if not eliminated, above Hesperia Dam. Restoring fish passage at both locations will expand access to 214 square miles of our 538 square mile watershed, and ideal spawning areas in the cold water stretches.
There may already be some fish passage across the spillways of White Cloud Dam now that the stoplogs have been removed. Alternative No. 4 would insure the status quo until the river is restored. For more details, please check with your local anglers, ideally above M-20.

Passive versus Active Restoration
The proposed revisions presented by Wade Trim have the potential to significantly reduce the cost of dam removal. In addition to the wetland issues discussed elsewhere in this article, several important details were not fully explained during the July 21, 2026, City Council presentation. Although many of these items may change during final design, understanding them now could help guide future decisions.
The estimated project cost of $5.2 million to $5.8 million depends on several variables, including:
- How much of the existing embankment will be removed.
- The length of the restored river channel, which is expected to be approximately the same whether the river is restored passively or actively. The White Cloud Dam Disposition Feasibility Study identifies a channel length of 5,300 linear feet with an average slope of 0.28 percent.
- The design and function of the proposed smaller two-stage channel.
River morphology is a specialized engineering field with relatively few qualified practitioners. Knowing who will lead this portion of the design—and understanding their qualifications and experience—will be critical to the project’s success. (See pages 51–53 of the White Cloud Dam Disposition Feasibility Study.)
Even under a passive restoration approach, disturbed soil must be stabilized to prevent erosion. A useful comparison is establishing a residential lawn: an active approach is like laying sod, while a passive approach relies on seeding and allowing the vegetation to become established naturally.
Sediment
Sediment has accumulated behind the dams for more than 125 years. The White Cloud Dam Disposition Feasibility Study estimates the approximate amount to be 1.158 million cubic yards of accumulated sediment, allowing for occasional floods that breached the dam. In an average year, about 10,250 cubic yards of “load” enters the impoundment.
The White Cloud Dam Disposition Feasibility Study recommends managing sediment throughout dam removal by using engineered controls, such as turbidity curtains, incremental dewatering and demolition, and construction methods such as selective sediment dredging. During the drawdown in the summer of 2025, considerable sediment was dislodged and flowed downstream, in spite of reassurance from the City’s engineer that there should be no problem.
Sea lamprey
The portion of the watershed above White Cloud Dam has been generally considered free of Sea lamprey. The White Cloud Dam Disposition Feasibility Study is mute on the issue, neither contending it functions as a physical barrier to Sea lamprey, nor the elimination of the dam would warrant new concerns.
Sea lamprey control is a primary goal of the Hesperia Dam replacement project. This function was supposedly incorporated into the design of Hesperia Dam when it was replaced in the 1970s.
However, those Sea lamprey are clever creatures. The watershed has potentially benefited from White Cloud Dam in the past. Lampricide treatment of the South Branch White River between the two dams has occurred in 2023 and 2026. M-37 was the upstream starting point three years ago. US Fish and Wildlife Service (USFWS) surveys allowed them to drop their starting point downstream to Baldwin Road this year.
At the City meeting Horak from EGLE’s Dam Safety Unit indicated he had been in touch with the Ludington USFWS office but reported no concerns.