White Cloud Dam
Dams and Impoundments Continued
White Cloud Dam [Municipal Power Plant Dam] and Lake White Cloud [White Cloud Dam Impoundment] on South Branch White River
[MI00526; 43.546, -85.767; Downstream Hazard Potential: High; Emergency Action Plan Required; Owner: City of White Cloud; Regulatory Authority: Part 315; Description: Retired hydro, earth concrete structure with height of 18.9 ft., head of 14.4 ft., normal freeboard of 3.5 ft., impoundment surface area of 50 acres, drainage area of 81.4 sq. mi.; Design Flood: 200 yr. with Design Flowrate of 2,600 cubic ft. / sec.; (for pre 6/26/2025 drawdown Max Rates of the dam, see White Cloud Dam Feasibility Study (February 14, 2025) page 176 of the pdf file. “The dam can safely convey up to the 2-year flood event.”); Condition Assessment: Poor]
White Cloud Dam – Chronology of Recent Events
Disposition Feasibility Study
Completed February 14, 2025, by GEI Consultants, the Feasibility study found major deficiencies in the dam’s structure and hydraulic capacity. There are two obvious approaches, either have a dam or remove the dam.
For having a dam, GEI Consultants points out that the current standards for the spillway capacity are subject to being increased should Michigan adopt standards developed by the US Army Corps of Engineers. They are already in place for federal dams. The Michigan Dam Safety Task Force in its 2021 report recommend their adoption. Therefore, GEI Consultants based their repair costs on the more stringent standard. The estimate ranges between $8.5M to $10.7M. The range reflects a broad range of uncertainty.
In addition to the larger spillway capacity requirements, the proposed dam safety regulations for High Hazard Dams will require more frequent and in-depth inspections, relicensing every 15 years, liability insurance to cover downstream losses, and financial assurances the City is able to pay for maintenance. The total cost in 2024 dollars for repair and 50 years of operation increase to $11.2M. If the proposed changes to the law occur right away, the total cost balloons to $18.6M. Funding to keep the dam are limited.
The removal option comes with two approaches. Passive restoration is less expensive but slower than active restoration. The estimated to cost for passive restoration is $9.3M while active restoration at $12.7M. There are no dam life cycle costs. Funding is more available.
Emergency Order
EGLE Dam Safety Unit reviewed Feasibility Study then asked the City to have GEI Consultants make a recommendation for the interim, while the City makes its decision. On that recommendation, on April 1, 2025, EGLE issued an Emergency Order to draw down lake 6–7 feet within two weeks. The order established that the City had to delineate the wetlands that would be exposed once the drawdown was completed. The drawdown starts a two-year countdown to avoid substantially greater wetland permitting requirements. The order also set a deadline for the City to select which option going forward it would take. If the repair/replace option were chosen, the City would need to demonstrate how it would fund the work. The start of November 2025 has become the negotiated deadline.
Deliberation and Negotiation
EGLE requires City to obtain a Joint Application Permit for the draw down, a step that was overlooked in the repair work done in 2024. When the City Manager received the estimate for the engineering services for this step, it also included rescuing stranded animals and delineate wetlands. Authorization of the total required a full meeting of the Council which finally was scheduled for May 19 as a special meeting.
Special Meeting, May 19, 2025
Originally anticipated to be a presentation by GEI Consultants on the entire study, the City Council limited its business agenda to consideration of proposals for the drawdown. GEI’s lead engineer and two representatives from Dam Safety Unit did take Council members’ questions. With reluctance, a majority of those voting ultimately accepted that the drawdown was to occur, but rejected unanimously the proposal from GEI Consultants. City Manager was granted approval to find a different engineer to prepare the permit. The City also wanted to hold off the start of drawdown unit after the annual Kids Fish Free tournament scheduled to be held June 7, 2025.
Public comments at the end of the meeting were numerous and adamant, uniformly in favor of keeping the dam.
Special Legal Counsel and Environmental Consultant
On June 24, the City’s recently hired attorney with special knowledge of dam removal projects provided City Manager a letter that made it clear the City must comply with the drawdown order or face fines. The letter introduced the City to the environmental consultant that was used for animal rescue during drawdown. It also confirmed that getting funding for repair/replacement of dams was near impossible.
Drawdown and Sediment
City hired new engineers to complete the Joint Application Permit, which EGLE approved June 25, 2025. Drawdown began that evening.
Though the City’s recently hired engineering firm had given EGLE assurance the drawdown rate of 1 foot per day would not cause sediment issues downstream, and in spite of the presence of the City’s hired environmental consultant and Dam Safety Unit engineer at the start of drawdown, sediment streamed over the dam. It went more than halfway to Hesperia.
After public outcry, intervention at EGLE by the City’s special attorney on their bequest, the drawdown was halted on July 4, 2025.
Special Meeting, July 21, 2025
The City’s special attorney made a presentation very similar to the fact included in the letter of June 24, 2025. With the environmental consultant, they provided examples of dam repair and removal projects within Michigan of similar size. The attorney indicated reported that should the City elect to repair the dam, it should anticipate it would have to issue bonds that would work much like getting a home mortgage.
Public comments following the presentation reflect a range of emotions form outrage to reluctant acceptance of their financial reality.
Meetings on August 5 and 12, 2025
On the first night, three prospective engineering firms presented their approach to how they would lead the City through the process of establishing a plan by the November deadline. The concept of removal while keeping a swimming pond was introduced. Each firm emphasized its capabilities at finding funding. Again, they reiterated that removal would be most likely to get funded.
At the follow up meeting a week later the Council voted to accept the proposal from Wade Trim. September 9, 2025, was set for the next Special Meeting when Wade Trim offered its review of the Disposition Feasibility Study and recommendations for going forward.
Update March 2026
City of White Cloud posted to its website an updated schedule for their dam replacement project dated March 24, 2026. At that point the City Council expected to receive an “Alternative Analysis Memo” from its consultant Wade Trim in June, 2026. The updated schedule also indicated that during the summer of 2026 the City would review and discuss alternatives with a vote to approve the selected alternative. Fundraising and grant efforts would then run from fall 2026 through fall 2027. Design and permitting to commence in the winter of 2027. Subject to funding and permitting, the City would bid and award construction contracts in the fall to winter of 2028. Again, subject to funding, construction would commence, at the earliest, in the winter of 2027.
This page provides access to the documents specific to White Cloud Dam. It is organized with the most recent item at the top. First time users may find it more informative to start at the bottom. This approach provides a history as the events unfolded.
The summaries are provided because many documents are technical. As to what has been included and to how it is explained, for this archive every attempt has been made to remain objective.
Much of the source material for this page was made available on the City of White Cloud website.
Public Notice EGLE Dam Safety Unit, October 21, 2025. (2 page pdf) As part of the permitting process for the Emergency Drawdown Permit of Lake White Cloud, EGLE’s Dam Safety Team exercised its prerogative to forgo public comments prior to issuing the permit. They stated “this is an after the fact notice for work previously completed.” The possible explanation for proceeding without public comment may be that its Emergency Order of April 1, 2025, required the drawdown be completed within two weeks. The actual Joint Application Permit for the draw down was not issued until June 25, 2025, with the drawdown beginning the same day. (See below details of the rejection of the permit preparation proposal from GEI Consultants, selection of Spalding DeDecker to prepare the application, and hiring of Streamside Eco for recovery and relocation of mussels.) In addition, before and after the draw down, Thomas Horak represented EGLE Dam Safety Unit at public hearings in White Cloud.
EGLE’s Public Notice created a 20-day period where “persons wanting to comment on the proposed project“ could use the MiEnviro Portal. Those cc’d include April Storms, White Cloud City Manager and Applicant; other City and Newaygo County offices; Aaron Snell, Streamside Eco; adjoining property owners; and other EGLE and DNR personnel. The comment period closed November 10, 2025, midnight.
PUBLIC NOTICE: EGLE Dam Drawdown Hearing – White Cloud Dam (2 page pdf). Posted to the City of White Cloud’s website where the link reads “PUBLIC NOTICE EGLE ACCEPTING COMMENTS – WC DAM.”
The link opens document titled PUBLIC NOTICE: EGLE Dam Drawdown Hearing – White Cloud Dam. The notice from City Manager April Storms begins, “The Michigan Department of Environment, Great Lakes, and Energy (EGLE) has scheduled a public hearing related to the Mill Pond Dam Drawdown Order.” “Although the drawdown was issued as an emergency order, EGLE is still required by law to hold a public hearing following permitting. This hearing provides an opportunity for the public to share comments, concerns, and feedback directly with EGLE regarding how the process was handled and the impacts experienced. ***This is the appropriate time and venue for residents to voice their input to EGLE regarding the drawdown order and its implementation. The Michigan Department of Environment, Great Lakes, and Energy (EGLE) Water Resources Division (WRD) has issued a Public Notice regarding the White Cloud Dam Drawdown. Although the drawdown was issued under an emergency order, EGLE is required by law to provide a public notice period for public comment following permitting. This is the public’s opportunity to submit comments directly to EGLE regarding how the drawdown was handled and the effects it has had. ~April Storms, City Manager”
[Bold face, red font color and capitalization sic from City’s website and public notice.]
A requirement of the Emergency Drawdown Permit, to be completed by October 1, 2025, was for the applicant (City of White Cloud) to make a determination of the before and after drawdown wetlands boundaries.
Evaluation of Wetlands Associated with Lake White Cloud September 2025 (18 page pdf available from MiEnviro Portal) Streamside Eco (Aaron Snell), under contract to City of White Cloud, states it is their opinion that all 52 acres of wetlands identified (14 existing – 1 lost + 39 new = 52 acres) will continue to exist if the drawdown is permanent, that this area is “regulated by EGLE” and will require permits before “any regulated activities” occur, such as excavating, filling, grading, construction, or draining.
Streamside Eco observed that at the upper reaches of the former impoundment, near where M20 crosses, the water surface dropped only about a foot, while closer to the dam approximately the full seven feet of the drop in lake level. “While it is difficult to predict long-term changes in hydrology associated with the lowering of the river and the water table, it is our professional opinion that, based upon current water levels, soil types and topography, most of the former impoundment bottom will remain wetland. Remnant stumps from trees show evidence of wetland conditions (e.g. buttressed roots) and provide a good indicator of wetland locations that existed prior to flooding of the impoundment. The biggest loss of hydrology is expected within +/-500 feet of the dam where the water surface dropped up to seven feet because of the drawdown; within this western area of the impoundment, the outer perimeter of the wetlands could disappear as the soil dries.”
White Cloud Dam Phase 1 Scope & Fee – (September 2, 2025) – Made available from the City of White Cloud website, the slides used by James Ensing of Wade Trim at the meeting of the City Council where the Council approved the firm’s $55.000 proposal. Of that, $40,000 is to go toward an “Alternative Analysis” that includes a reevaluation of the repair/replace and active/passive removal options covered in the Disposition Feasibility Study completed in the spring of 2025 by GEI Consultants.
Newaygo County Public Opinion – Near North Now – (August 1, 2025) “For the Health of the River” – The White River Watershed Partnership weighs in on the White Cloud dam. The letter from the WRWP Board points out the thermal impact of the impoundment, lets readers know that the stretch between White Cloud Dam and Hesperia Dam is capable of being a “world class fishery.” WRWP’s position is that the drawdown could have been less aggressive, but we anticipate the river channel to reestablish itself fully. In addition, for the safety of those downstream, because of the crippling debt, costs of never ending maintenance and insurance that in the future would fall on the citizens of White Cloud, for unobstructed fish access to the upper river, cooler water temperatures between the dams at White Cloud and Hesperia, and to again allow nutrients to move freely through the river channel, the dam must be removed.
On August 13, WRWP’s letter also appeared in Fremont’s Times Indicator.
White Cloud City Council Special Meeting Minutes (July 21, 2025) – City Clerks minutes of the second special
meeting of the Council on the dam. It had been nine weeks since the last public meeting where all public comments were in favor of saving the dam and lake. It had been twenty six days since drawdown had begun. Because concerned citizens downstream had complained about excessive sedimentation from the impoundment, the City had its special council intervene with the Dam Safety Unit resulting in a temporary halt of the drawdown. The last stoplog had been removed July 3, 2025.
Not included in the minutes from its Special Meeting of July 21 is the Mayor’s statement where he expressed concern over social media posts that amounted to “misrepresentation” of the City’s actions. He emphasized that the Council and City Manager have done what must be done to comply with the law.
Next the Mayor turned the proceedings over to Stacy Hissong, the City’s specialist attorney hired following the last public meeting. She sat at a table between the dias and public gallery, flanked by Aaron Snell of Streamside Eco and Thomas Horak, EGLE Dam Safety Unit engineer.
These minutes summarize Hissong’s PowerPoint presentation. Much like the letter she had sent to the City Manager June 24, Hissong’s presentation this evening laid out the City’s situation: few if any funds are available for restoration or repair. To save the dam, the 1400 citizens of White Cloud could either pass a special millage on the full city, or a special assessment district of the property owners around Lake White Cloud. Hossong had talked to underwriters of municipal bonds about White Cloud. Not sure any underwriters would be interested in dam replacement, she explained a bond issue would work much like a home mortgage. Current interest rates are 5 to 6%.
Hissong, Snell and Horak covered several deadlines. Wetland delineation must be done by the start of October, 2025. To avoid significant added wetland mitigation requirements, the project must commence permitting within two years of the start of the drawdown. Finally, the City must have a plan of action with potential funding completed and submitted to EGLE’s Dam Safety Unit by early November. Horak offered that EGLE would be flexible if there is steady progress.
Aaron Snell had been recommended by Hissong and then hired by the City to insure stranded mussels and other animals would be moved from the lakebed during the drawdown. At this meeting he talked about Lake Kathleen Dam removal, a project he had worked on that was similar in size to Lake White Cloud. Located on the Maple River near Pellston, Michigan, about 20 miles south of The Bridge, the removal was completed in 2019 for only $2.3M using “passive restoration” techniques to reduce the amount spent. By contrast, according to Snell and Hissong there was the Forest Lake Dam full restoration near Alger, Michigan. It ended up costing about $13M, which reportedly was double the original estimate. According to Hissong, the ARPA funds used for that project are no longer available.
Only those in attendance who completed a testimony/comment card were permitted to speak during the public comment portion of the meeting. When Hissong called a name from a card, a runner took the mike to the person, and the clerk started the digital clock used as the two-minute countdown timer. The meeting minutes includes a list of approximately three dozen who participated, but regrettably the minutes are not a record of what was said.
WRWP had four board members in attendance, none submitting a card or spoke. Prior to and following the meeting, Horak and Snell confirmed to WRWP board members they had been on site during much of the early drawdown.
Newaygo County Public Opinion – Near North Now – (July 17, 2025) “Dam Controversy Comes from State” – Newaygo County Drain Commissioner Dale Twing makes the case to save the dam, contending it is needed for Sea lamprey control because Hesperia Dam is not effective and that in spite of the warming, as a life-long trout fisherman and student of history, the White is a great fishery above and below the dam and always has been.
Comment from Michelle Petz (July 24, 2025) states that structural concerns are serious. Simply adding a spillway or lowering the water level may not adequately address the underlying safety risks.
EGLE Water Quality Monitoring downstream of dam conducted July 15, 2025 – From posting on the City of White Cloud’s website. On July 16, 2025 Lucas Trumble, EGLE Dam Safety Unit, sent Stacy Hissong, attorney to the City, and Aaron Snell, environmental consultant with StreamsideEco, the results of turbidity, dissolved oxygen and temperature testing conducted the day before. The tests were taken by Connor O’Brien of EGLE’s Groundwater Discharge Compliance staff, stationed in Grand Rapids.
Trumble indicates EGLE doesn’t get concerned about long-term exposure to fish unless turbidity get to 50 NTU (Nephelometric Turbidity Units) above background levels (White River at 2 Mile Rd,) for more than 7 days, or Dissolved Oxygen levels drops below 5 mg/L. The following tests were taken 20 days after the drawdown had started.
EGLE Water Quality Testing following Drawdown of White Cloud Dam (Day 20)

City of White Cloud, Dam Drawdown Update (July 8, 2025) – Day 8 of the Drawdown. City Manager Storms had gotten their attorney to talk with Lucas Trumble, Supervisor, EGLE Dam Safety Unit, about the sediment. Storms indicated the resolution was to stop the drawdown for the balance of the week. “The approach will remain flexible, with boards being removed or reinstalled as needed to support the health and restoration of the river ecosystem.”
On the evening of June 25, 2025, the first stoplogs were removed, and the drawdown had begun. Within days, considerable sediment was being observed as far as 14 miles downstream, where M20 crosses the river. City of White Cloud, City Manager to White Cloud Community (June 25, 2025) – Confirmation that Fahey Schultz Burzych Rhodes (FSBR) had been hired, that FSBR had met with EGLE (most likely Lucas Trumbel and Tom Horak) on June 20, 2025. City Manager asked FSBR “is it viable to continue challenging this process from a legal standpoint?” The response was “the only remaining viable option is to proceed with the required permit and drawdown of the Mill Pond water. This path allows us to avoid steep fines, environmental violations, and significant legal and liability costs.” As to the timing of the drawdown, City Manager Storms writes, “Beginning this evening, June 25th, the city will commence the drawdown process with our legal team, contractors and EGLE/DNR. The DPW (Department of Public Works) will remove one board per day from the dam over the course of 5–7 days. This process will be conducted under environmental supervision to ensure the water level is lowered in a controlled and responsible manner.” As to the timetable for wetlands, “Once the drawdown begins, the State provides a two-year window before the exposed area is considered permanent wetland. After that, restoration becomes far more difficult, if not impossible.” To the future, “The city has essentially two potential options: rebuilding and rehabilitation of the dam or dam removal. Costs for removing the dam were estimated at $9.3-$12.7 million, whereas repair estimates ranging as high as $18.6 million over the next 50 years (with those costs increasing significantly once adjusted for up to 50 years of inflation). Unfortunately, while there are numerous funding opportunities available for dam removal, river restoration, and the creation or restoration of recreational assets such as a man-made swimming lake, there is very limited funding available for dam rehabilitation or reconstruction. As such, a key priority moving forward will be identifying potential funding sources based on the direction ultimately chosen.”
EGLE Notice of Authorization (June 25, 2025) – Document to be posted at the dam site.
Emergency Permit for Drawdown HQD-4BA5-3H0ND (June 25, 2025) – From EGLE to White Cloud City Manager. “Conditional Permit. This permit is granted conditionally under circumstance of emergency or urgency to protect property or the public health, safety, or welfare. Under emergency conditions, drawdown Lake White Cloud to the extent possible by removing all stoplogs from the primary spillway and auxiliary spillway. The drawdown rate is not to exceed one (1) vertical foot per day. The removal of all stoplogs at the dam is expected to lower the impoundment by approximately seven (7) vertical feet and reduce its size by approximately 25.2 acres.”
From on-site observation, WRWP board members Schinler and Stivers noticed several of the removed stoplogs within the fence around the Auxiliary Spillway. They were neither 6” nor 12” in width, but appeared near the size of a nominal 2” x 8”. By virtue that stoplogs are generally custom made, milled and cut to order from special species of wood, those at White Cloud Dam may have been exactly 8”.
On June 24, 2025, White River Watershed Collaborative. At the invitation of Jake Lemon, EGLE Dam Safety Unit engineer Thomas Horak spoke to over two dozen participants on the Zoom meeting. Several WRWP board members were in attendance. Horak indicated the City of White Cloud’s engineer (Spencer DeDecker, hired specifically to complete the Joint Permit Application) and EGLE had settled upon drawdown of a foot per day until the lake level has been dropped six to seven feet. Horak stated approval was close. He indicated the City must come up with a plan by early November to either remove the dam or replace it. If they elect to rebuild, the plan needs to demonstrate how they will fund it. The Emergency Order requires a wetlands delineation by the start of October. When questioned, he indicated that the City is responsible for preventing people from the danger of walking into the mucky lakebed.
Letter from Stacy L. Hissong, Member Fahey Schultz Burzych Rhodes Attorneys at Law to April Storms, City Manager, White Cloud (June 24, 2025) – After being hired by the City, Stacy Hissong outlined the situation, starting by stating that EGLE ordered the City to complete a feasibility study to determine what type of rehabilitation may be necessary. She writes: “That study found that “The White Cloud Dam is an aging piece of infrastructure” with “multiple deficiencies” that needed to be addressed. (Feasibility Study, p 56.) The study identified essentially two potential options: repair the dam or remove it. Costs for removing the dam were estimated at $9.3-$ 12.7 million, whereas repair would be significantly more expensive, with estimates ranging as high as $ 18.6 million over the next 50 years (with those costs increasing significantly once adjusted for up to 50 years of inflation). (Feasibility study, p 56-57.)”
She continues: “ln response to this feasibility study, EGLE issued a letter on April l, 2025, to the City noting that the report identifies “significant issues at the dam” that may require “immediate risk reduction measures” while a long-term plan for the dam is being developed.” “ln response to this feasibility study, EGLE issued a letter on April l, 2025, to the City noting that the report identifies “significant issues at the dam” that may require “immediate risk reduction measures” while a long-term plan for the dam is being developed.” “Michigan law requires that’ if a dam owner’s engineer finds a condition that endangers a dam, EGLE is required to order the dam owner to take actions necessary to alleviate the danger. MCL 324.31518(7).
Based on that requirement, on April 18, EGLE issued an order requiring the City take action on an expedited schedule. (Correspondence, pp 4345.) Specifically, EGLE ordered the City to apply for a permit to draw down the impoundment by 6 to 7 feet within two weeks and then initiate the drawdown when authorized to by EGLE. The new order also significantly expedited the City’s timelines for developing schedules and plans for short-term and long-term remedial measures.” In this correspondence, the City’s “outside counsel with experience in Michigan’s dam safety laws” covered the liabilities associated with failure to comply with the EGLE order.
The letter included a recommendation of StreamsideEco (Aaron Snell) to assist with the rescue and relocation of stranded mussels and fish.
Joint Permit Application for Emergency Drawdown of White Cloud Lake (Permit HQD-4BA5-3H0ND) (June 20, 2025) – (18 page pdf.) – For permit applications EGLE uses portal, open to public view, that shows all the documents and the actual permit, including the dialogue between the State and applicant as it is being prepared. Once the City had voted to reject the proposal from GEI Consultants for this work, it selected and hired Spalding DeDecker. To complete the application, a licensed engineer is required. For this purpose, White Cloud provided a letter to EGLE designating an engineer within Spalding DeDecker as the City’s agent. The Permit captures the discussion notes between EGLE Dam Safety Unit engineer and Land/Water Interface Permitting staff member in Grand Rapids, with representatives from Spalding DeDecker.
Though not hired, the application indicated that ASTI Environmental would do the recovery and relocation of muscles; subsequently the work was performed by Aaron Snell of Streamside Eco.
The exchange of questions and responses in the permit application showed possible lack of knowledge of the actual gates and stoplogs. While GEI Consultants had previously recommended the drawdown be only 7 feet, this recommendation was inconsistent with the another recommending all the stoplogs in the center gate of the primary spillway were removed. The bottom to the center gate is over 9 feet below the common lake level. By the end of the permitting process, a drawdown of 7 feet had been selected. Working on the possible assumption the stoplogs were 6”, the applicant (Spalding DeDecker in behalf of City of White Cloud) proposed removing three per day, which would have been 1.5 feet/day. When questioned by EGLE, Spalding DeDecker reverted to a foot per day, adding it to be the “appropriate drawdown speed to avoid velocities which would suspend sediment along with allowing for efficient relocation of stranded organisms.” Spalding DeDecker responded again with, “Based on the currently available information, it is estimated that the velocity of flow created by the drawdown within the impoundment is below that which would result in sediment suspension. Additionally, it is estimated that the existing sediment at the downstream end of the impoundment is below the bottom of the estimated water surface after the drawdown has been completed and all logs have been removed.”
Authorization Letter from White Cloud City Manager to Spalding DeDecker (June 10, 2025) – From EGLE permit portal, the letter designating the engineer at Spalding DeDecker who would act as City’s agent in matters related to the Joint Permit Application required by EGLE for the dam drawdown. Again, the City of White Cloud selected Spalding DeDecker after not accepting GEI Consultant’s proposal for permit application at the Special Meeting of the City Council on May 19, 2025.
Michigan small town fights order to lower lake behind risky old dam (June 4, 2025) – Mlive story by Garret Ellison (possibly behind a paywall), covering the history of the dam and the position the City of White Cloud has taken.
City of White Cloud Summer 2025 Newsletter City Manager Update – Posted on the City of White Cloud website, the portion of the newsletter where the city manager indicates that despite of the City’s ongoing efforts, EGLE is still requiring an emergency drawdown. There is an admission that the City may be forced to comply with the directive short term, but that they plan to reach out to state legislators, and have requested the opportunity to testify before the House of Representatives Appeal Board to speak out against the misuse of a study the City feels was initiated in good faith, but is now being used to dismantle the dam. 
White Cloud City Council Special Meeting minutes (May 19, 2025) – Posted on the City of White Cloud website, the minutes from the special meeting where the council voted against the motion to approve expenditure for GEI Consultants of $40,000 for completion of the Joint Permit Application to EGLE. During the meeting, the project engineer from GEI Consultants stated there was $6000 for wetland delineation and $18,000 for stranded organism monitoring. Before the vote, he offered to make the quote “not to exceed.” The motion failed. A second motion was introduced authorizing the city manager to obtain cost estimates from other engineering firms for the EGLE permit application with the drawdown to being on or after June 9th. The motion carried.
White Cloud Dam Correspondence (April 1, 2025 – May 19, 2025) – Posted to the City of White Cloud website, the correspondence between the city manager, GEI Consultants project engineer, and individuals of EGLE Dam Safety Unit. The exchange includes EGLE’s request to the City that it have their engineer, GEI Consultants, make a recommendation concerning short-term actions (drawdown of Lake White Cloud).
Agenda, May 19, 2025 Special Meeting where GEI Consultants was intended to explain recommendation for drawdown of Lake White Cloud
May 15, 2025 Memo from City Manager to Council indicating the business at the Special Meeting on May 19 is “strictly about whether or not the city will fund the permit process tied to EGLE’s recent directive in the amount of $40,000,” which is the amount of GEI’s proposal.
It also includes a recommendation from the City Attorney for Mayor Miller and Councilmember Shear to abstain from voting due to a potential appearance of conflict of interests. They either own or reside along the river.
City Manager provides update on meeting with Michigan 101 District House Representative Joseph Fox where he “agrees with our stance” EGLE is weaponizing the feasibility study, attempting to enforce an unfunded mandate with no real opportunity to respond or plan. The City Manager adds that EGLE is “overstating the risks associated with the dam to further an agenda that is not reflective of the true condition. She is adamant: “Furthermore, I believe that EGLE’s behavior is both unreasonable and unethical. Using a feasibility study that we agreed to participate in cooperatively as part of a grant requirement-only to then turn it into a mandate-is an abuse of public trust.”
May 5, 2025 GEI Consultants submits a “time and material” proposal for the permitting of the emergency drawdown.
Excerpt of Natural Resources and Environmental Protection Act concerning dams (possibly supplied by GEI Consultants) with highlighted sections pertinent to Emergency Orders. These 12 pages are the rules under which EGLE works with dam owners, and the consequences of non-compliance. Also in these pages are timeline for compliance, dam spillway capacity requirements, and inspection report requirements. (Pages 9 – 20 of this pdf.)
May 7, 2025 Notification to residents of May 19 Special Meeting. In the notification is reference to a meeting on April 30, 2025 between the Mayor, City Manager, EGLE representatives and GEI Consultants that gave the city the time to approve the funding needed for the drawdown permit, but with the stipulation that drawdown must begin no later than June 9, 2025, if permit approved. The City Manager also wrote the State’s action is “built upon a narrative on imminent risk that is not supported by the historical record, including the 1986 dam failure, which, while significant, did not result in loss of life even under poorer conditions and less oversight than today.”
May 7, 2025 From City Manager to Dam Safety Unit engineer Thomas Horak, with copies to Senator Slotkin, and Michigan House Representative and Senator, that while the City had received the recommendation from GEI Consultants on April 18, 2025, and had agreed to the actions that EGLE had requested, the City had not anticipated the $40,000 proposal needed to get the drawdown permit.
May 1, 2025. Proposal from GEI Consultants for Permitting Support.
April 23, 2025 to City Manager from Dam Safety Unit engineer acknowledges City’s desire to consult with its engineer, then adds, “EGLE will still recommend that a permit application be submitted as soon as practicable to start the process.”
April 18, 2025 to City Manager from Dam Safety Unit engineer restating Order sent April 1.
Other correspondence in regard to above requirements.
April 1, 2025 to City Manager from Dam Safety Unit engineer. The Order.
You are hereby ordered under Section 324.31 518 to take the following corrective
actions:
1. Develop a high-level plan and schedule to address the deficiencies at the dam.
This plan will help us set reasonable deadlines for making both short term and
long term decisions and carrying out those decided upon remedial actions.
Please provide this plan for review by May 1. 2025. The schedule should include
the following deadlines. and the intermediate milestones needed to reach them.
2. Finalize a plan for interim risk reduction measures. This plan may include interim
repairs, drawdown. or other measures. Implement the plan as soon as
practicable. This plan will likely require input from your engineer and a permit
from EGLE. Provide the plan to EGLE for review by June 2, 2025.
3. Finalize a plan for long-term remedial action. This plan should include a repair or
removal plan, or a proposal for an alternative dam modification project. Provide
this plan to EGLE for review by November 3,2025.
April 4, 2025 to City Manager from Janeen McDermott and Dan DeVaun of GEI Consultants confirming in extensive detail the reasons for their recommendation:
Given the identified deficiencies at the dam and the elevated risk of dam failure, GEI recommends the City pursue an immediate drawdown of the impoundment to the extent practicable. This drawdown will need to be implemented in coordina6on with Michigan Department of Environment, Great Lakes, and Energy (EGLE) Dam Safety unit. and following receipt of a permit from EGLE.
White Cloud Dam Feasibility Study (February 14, 2025) – Posted on the City of White Cloud website, the entire 326 page study completed by GEI Consultants of Michigan, P.C. was commissioned under the 2023 EGEG grant to the City of White Cloud.
After a visual inspection in 2022 by EGLE’s Dam Safety Unit, it awarded the City of White Cloud a total of $291,137 from the 2023 – 2024 Dam Risk Reduction Grant Program. The repairs that were visually recognized during that 2022 inspection were funded but with the understanding that a much more detailed assessment was needed. Hence the stipulation and award of over $100,000 for the Disposition Feasibility Study.
This study did not predict odds if, when or how the dam might fail. Nor did it update the value of property that might be lost should it fail. In its path is a railroad trellis, M37 bridge, a sewage treatment facility, and over a hundred residential parcels. The study did model in detail the hydrology, that is the amount and rate of water coming into the impoundment. It then assessed the hydraulic capability of the dam’s gates to discharge that water. It was found that the dam could not pass the legally required 200-year storm event. In fact, (page 28, paragraph 3.1.4 of the pdf.) the analysis found that at normal summer pool level the dam would overtop during in a 5-year storm event if none of the stop logs were removed.
In all the scenarios run, the assumption was that the ground upstream of Lake White Cloud was “not completely saturated or completely dry.” If those soils were saturated from recent rainfall, potentially what occurred in 1986 when it last failed, the likelihood of overtopping goes up. The City of White Cloud terminated its agreement with GEI Consultants shortly after EGLE issuing the drawdown order; as a result, no hydraulic modeling has been done to determine the dam’s capacity in its drawn-down state. No place does the study suggest that the dam’s problems could be solved by just adding another spillway.
The reverse engineering of the earth embankments determined that the factor of safety was less than the U.S. Army Corps of Engineers’ minimum. At normal pool the factor of safety was 1.2 versus 1.5, and flood pool 1.1 versus 1.4.
The primary spillway inlet structure, where the three gates are located, does not meet the minimum stability criteria based on current industry standards for overturning. In addition, the wing walls that hold the stoplogs and gates were found “NOT” (their emphasis) to be in compliance with current design guidelines.
Based on these findings, GEI Consultants developed several project scenarios, each with estimated project and on-going maintenance costs. They made the observation that currently government funds to restore or replace the dam are in short supply.
After reviewing the report, EGLE’s Dam Safety Unit asked the City of White Cloud to have GEI Consultants make a recommendation based on the Study. GEI’s recommendation resulted in EGLE’s April 1 order, the immediate emergency step to be the drawdown White Cloud Lake. Also see White Cloud Dam Correspondence (April 1,2025 – May 19, 2025)
WRWP letter to the EGLE Dam Safety Unit (December 2024) – WRWP’s letter in opposition to EGLE awarding a second grant addendum to cover the repairs to the bridge where S. State Street crosses over the Primary Spillway. None the less, the State awarded 85% of the $46,000 total.
White Cloud Dam Operations & Maintenance Manual (2019) and Newaygo County White River Emergency Plan for Dam Failure and Flooding (2017 Edition) – Posted on the City of White Cloud website. The Operations & Maintenance Manual (13 pages) was prepared by OMM Engineering, the same firm that engineered the reconstruction after the dam breach of September 1986, a set of those 1989 documents are included (11 pages) in the Disposition Feasibility Study. The O&M manual includes a timeline of the dam’s history, from first constructed in 1872, through two failures from floods in 1910 and 1986, the dam crest being elevated in 1975, addition of the auxiliary spillway in 1978, and the addition of the roller-compacted concrete (RCC) overflow spillway with the reconstruction in 1990.
The manual, intended for the City of White Cloud’s Department of Public Works, provides procedures to discharge cooler water from below the surface; none the less, recent comparisons of water temperature recorded by two EnviroDIY monitors, one above and the other below the impoundment, demonstrate the impoundment increases summer water temperatures around 10◦F. In all caps, the manual warns that the stoplogs and slide gates cannot be left at normal-pool configurations when there is a major storm. Any rain event that causes the lake level to continue rising after all the stoplogs have been removed warrants the operator to declare a state of emergency.
The Emergency Plan (52 pages) was prepared by the Newaygo County Emergency Services Department, and authorized by both Abigail Watkins, the County Emergency Services Director, and Don Barnhard, White Cloud Mayor at the time signing. The plan covers the response for flood conditions, then has a dedicated dam failure specific annex.
Response plans are predicated on the severity of the situation, from “dam failure is imminent or has occurred” to “the Grand Rapids national weather service issuance of a flash flood watch.” The plan anticipates the need to monitor nine bridges over the South Branch between White Cloud and Hesperia. Working downstream they run from the Pere Marquette Railroad Bridge, first below the dam, to Dickinson Ave. bridge a mile east of Hesperia.
Explicitly stated, the plan does not rule out that failure of the White Cloud Dam would cause the Hesperia Dam to fail. In the most sever situation, where the White Cloud dam has failed or it is imminent, notification to evacuate is to be given to residents as far downstream as W. View Drive, which is northwest of the M20 White River Roadside Park. In 2016 when the annex was written, 105 homes would need to be notified along this 16-mile stretch of the river.
White Cloud Lake Rare Species Review (December 5, 2023) – Letter and report from Michael Sanders, Environmental Review Specialist/Zoologist, Michigan Natural Features Inventory, MSU Extension to GEI Consultants as part of input for the White Cloud Dam Feasibility Study. The report covers six species within 1.5 miles of the lake that are either threatened or endangered, or special concern species or natural communities. (9 pages)
Twenty-two Michigan dams get safety upgrade funding through risk-reduction program (May 6, 2024) – Link to EGLE website that announced recipients of the 2023 – 2024 funding cycle of the $14.1 million Dam Risk Reduction Grant Program from the Michigan Department of Environment, Great Lakes, and Energy (EGLE), that is administered by the Dam Safety Unit. Of the 20 projects statewide, two were within the White River Watershed:
- Hesperia, $270,000: To the village of Hesperia to investigate the current condition of the Hesperia Dam on the White River. The study will identify, analyze, and assess risks. Initial tasks will focus on data collection through desktop exercises and field data collection. Remediation measures will be developed to address deficiencies and bring the dams into compliance with safety requirements.
- White Cloud, $68,425: To the city of White Cloud to support the completion of a dam disposition feasibility study for White Cloud Dam. This study will help the city make informed decisions on the future of the high-hazard dam on the White River and will consider dam removal situations.
In May of 2023, EGLE granted White Cloud the initial $222,712. In early 2025, after construction bids came in above engineer estimates for the repairs identified during the State’s 2022 visual inspection, EGLE amended the grant by $68,425, restoring adequate funds to cover the disposition feasibility study. In early 2025, EGLE again amended the grant to cover repairs to the bridge structure on South State Street over the primary spillway. To date, approximately $342,500 has been spent, with the State of Michigan picking up 85% or $291,137, while the City of White Cloud is out over $51,000.
White Cloud Dam Safety Inspection Report (December 2022) – (88 pages) – On May 25, 2022, the 3-year inspection of White Cloud Dam was conducted. The report was prepared by Thomas Horak and Lucas Trumble of the Dam Safety Unit. The inspection was a visual inspection. Photos are included with the report. Similar to the 2019 inspection, the dam was found to be in Fair condition.
There were 14 recommendations, starting with an updated hydraulic analysis – the dam’s capacity to pass storm water – in light of recent overtopping and near overtopping events. The others included repair of the left gate of the primary spillway and concrete and metal repairs dating from a 2015 report from the engineers of the replacement dam. Seepage issues were noted with recommendation to improve vegetation removal and routinely inspect. Wave action erosion along the lake shore and auxiliary spillway should be addressed with rip rap armoring.
In the judgment of the report authors, the High hazard potential to life and property downstream remained appropriate.
White Cloud Dam Removal Preliminary Analysis, prepared by Trout Unlimited. Obtained from City of White Cloud website (71 pages). This report is not dated but, by virtue of the references, was apparently completed by early 2022, which is approximately two years following the May 19, 2020 failures of both Edenville and Sanford Dams near Midland, Michigan. Included in the report are two maps prepared in 2021 by Michigan Department of Environment Great Lakes and Energy (EGLE) Dam Safety Program that show the 2500 regulated dams, and the 3.5% classified as creating a High Hazard potential should they fail. White Cloud Dam is included as one.
The report summarizes the 2019 White Cloud Dam inspected done by Dan DeVaun, who was then the lead engineer of the Dam Safety Program. That inspection stipulated the need for repairs and changes to operations. In T.U.’s report, they outline a list of work being done between inspections occurring in 2019 and 2022. For their report T.U. was told by the city manager at the time that an additional $50,000 and $100,000 per year should be budgeted for this type of on-going maintenance.
Trout Unlimited through its report provided the City of White Cloud a concise three-page explanation of the dam removal process. It described what the exposed lake bed would look like. They went so far as to have a Grand Rapids real-estate agent determined property with frontage on the White River was more valuable than on Lake White Cloud.
The T.U. report explains that once the water level of Lake White Cloud is dropped, the river has the potential to cut a deeper channel. Attention should be given piers and banks of the M20 Bridge east of downtown so they are not undercut. Appendix C includes a 30-page copy of the bridge plans.
Concluding the report are two conceptual renderings by a landscape architect of what the area might look like once restored.
EGLE MiEnviro Portal – The White Cloud Dam documents from the EGLE Dam Safety Unit are available here, or using this link.
White Cloud Dam Safety Inspection Report (October 2019) – (37 pages) – On July 19, 2019 the 3-year inspection of White Cloud Dam was conducted. The report was prepared by Daniel DeVaun of the Hydrologic Studies and Dam Safety Unit, Department of Environmental Quality. After leaving the State, he was the lead engineer of the White Cloud Dam Disposition Feasibility Study by GEI Consultants. The inspection was a visual inspection. Photos are included with the report. The dam was found to be in Fair condition.
There were 6 recommendations, starting with an updated hydraulic analysis – the dam’s capacity to pass storm water. The report called for the City to develop and implement concrete repairs to the primary and auxiliary spillways within three years. The report called for vegetation removal on the downstream side of the embankment. An update of the 2013 Emergency Action Plan was requested.
In the judgement of the report author, the High hazard potential to life and property downstream remained appropriate.

Reconstruction following flood of September 1986.
City of White Cloud was denied a permit to reconstruct the dam by the Michigan Department of Natural Resources. The DNR contended the river would fair better without the dam.
To get around the denial, the region’s state senator Phil Arthurhultz sponsored two bills in1988. House Legislative Analysis for Senate Bills 1038 and 1039. (2 page pdf)
At this point FEMA had taken a counter position, contending the repairs would not significantly impact the environment. It was willing to fund nearly all of the cost for the dam’s replacement and reportedly the City of White Cloud had overwhelming voted to raise taxes to cover the balance.
When the bills became law, they amended the Dam Safety portion of the Michigan Environmental Protection Act and the Inland Lakes and Streams Act so permit requirements would not apply to dams in Everett Township in Newaygo County (White Cloud Dam) and the Village of Luther in Lake County, and only those dams that were over 75 years old when they had been damaged or destroyed by an act of God in 1986. This highly specific waiver was to be in effect for three years.
Proponents for the exemption pointed out that the DNR had singled out just these two dams for permit denial. The battle lines were drawn between those who felt the dam and impoundment were integral parts of their community, and those who felt that already in the absence of the White Cloud Dam there had been improvement in the trout population in the watershed.
During this three-year period, engineering documents still had to get final approval from the Joint Capital Outlay Committee of the legislature. Important environmental and public safety standards concerning underspillway devices, minimum flow releases and removal of contaminated sediments were still required.
Trout Unlimited, Muskegon-White River Chapter v. City of White Cloud – (numerous legal summaries appear when searched) – With reconstruction of the dam underway in the summer of 1990, Trout Unlimited, Muskegon-White River Chapter brought suit in an attempt to stop work. As plaintiffs, T.U. alleged the dam was unlawfully reconstructed and raised claims of fraud, violation of public trust, violation of constitution prohibitions on local legislation, and failure to obtain necessary approvals from state and county authorities.
The judge in a bench trial concluded that trout were not rare, unique or endangered, that only a small portion of the Middle White River had the potential to become a blue-ribbon trout stream in absence of the dam. “In effect, the plaintiffs seek to have the City create a natural resource.”
The judge made no ruling on the validity of the actions taken by the State Legislature. On T.U.’s appeal, the appellate court found that the flood was “an act of God” and warranted defendant’s deliberate breaching of the dam. However, it also found that organizations such as T.U. did in fact have standing to bring such a suit based on provisions in the Michigan Environmental Protection Act that allow private parties to initiate lawsuits for declaratory and injunctive relief to protect natural resources. That ruling made Michigan law, and since has been cited in numerous suits brought on behalf of environmental groups.
To ensure standing, T.U.’s council added Richard McEwen as a plaintiff. He was possibly president of the now defunct Muskegon-White River T.U. chapter. McEwen died December 8, 2024 at 91. He had been president of Muskegon Sportfish Association, and helped create the artificial Hamilton Reef (aka “The Rock Pile”) in Lake Michigan south of the Muskegon Channel out from Muskegon’s Pere Marquette Park. McEwen was instrumental in the introduction of Walleye into the Muskegon Watershed. We was co-founder of the company that produced the Mac-Jac Downrigger.